PUBLIC PROCUREMENT | PRACTICAL GUIDE
Cochabamba, November 2026
On November 16, 2026, Supreme Decree No. 5775 was issued, establishing exceptional mechanisms to adjust prices in public works and technical supervision contracts, given the rising cost of materials, machinery, equipment and diesel.
In simple terms: if you are building a project for the State and your inputs went up, the decree gives you ways to readjust the contract, request additional advances or, if the adjustment is not viable, terminate the contract without penalties.
> The deadline to sign amendment contracts is December 31, 2027.
1. Key figures
| Figure | What it means |
|---|---|
| 540 days | Initial contract term that determines which adjustment regime applies. |
| 7 inputs | Maximum number of critical inputs in the adjustment formula. |
| 70% | Inputs are chosen from the largest items adding up to 70% of the contract. |
| 12/31/2027 | Last day to sign amendment contracts. |
2. Two regimes depending on the term of the works
| | Initial term up to 540 days | Initial term over 540 days |
|---|---|---|
| How it is adjusted | One time only, through an amendment contract | Polynomial adjustment formula |
| What is adjusted | Only the material price (Form B-2), without indirect costs | Up to 7 critical inputs, chosen from items adding up to 70% of the contract |
| What it covers | Materials, machinery, equipment and diesel | The inputs in the formula |
| On what amount | The balance still to be executed | Applies until the contract ends |
| Who calculates it | The entity, supported by the contractor | Contractor and supervisor build the formula |
3. Additional advance or materials in storage
The contractor may choose only one of these options:
| Option | How it works | Guarantee |
|---|---|---|
| Additional advance | Up to the cost of pending inputs | 100% guarantee |
| Materials in storage | Up to 80% of stored materials is paid, and the remaining 20% when placed on site | Insurance policy |
4. Technical supervision
The supervision contract amount may also be increased through an amendment contract, following a report from the works inspector. The supervisor must provide an updated guarantee of 7% of the total increase.
5. Limits and exits
| Situation | What the decree says |
|---|---|
| Works already adjusted | Works adjusted under SD 5321, 5406 and 5597 only access later price variations. Adjustments already recognized become the new baseline. |
| No available funds | The entity may reduce the scope of the works without affecting their functionality. Autonomous governments may allocate additional resources. |
| Adjustment not viable | Entity and contractor may terminate the contract for force majeure: no SICOES debarment, no guarantee enforcement and no damages. |
6. Which works does it cover and since when?
The decree is in force since its publication. It applies to works already awarded and to ongoing processes with external financing. The guide to apply the polynomial formula will be approved by Bi-Ministerial Resolution within 10 business days.
7. Risks for contractors
| Risk | Why it matters |
|---|---|
| Missing the deadline | After December 31, 2027, amendment contracts can no longer be signed under this decree. |
| Insufficient support | Without organized invoices, quotes and records, the amount recognized may be lower. |
| Choosing the wrong option | You can choose either the additional advance or materials in storage, not both. |
| Cost of guarantees | The advance requires a 100% guarantee and supervision a 7% guarantee on the increase. |
8. Checklist: what to do now
| Step | Action |
|---|---|
| 1 | Identify your current works and supervision contracts and their initial term (up to or over 540 days). |
| 2 | Calculate the balance to be executed and the inputs that rose the most. |
| 3 | Gather price evidence: invoices, quotes and indices. |
| 4 | Check whether your works were already adjusted under SD 5321, 5406 or 5597. |
| 5 | Decide whether the additional advance or payment for stored materials suits you better. |
| 6 | Wait for the polynomial formula guide (10 business days) and file your request in time. |
9. Frequently asked questions
Is the adjustment automatic?
No. It is formalized through an amendment contract and requires analysis by the entity, the contractor and the supervisor.
Are indirect costs also adjusted?
For works of up to 540 days, no: only the material price (Form B-2).
What if the entity has no budget?
It may reduce the scope of the works without affecting their functionality; if the adjustment is not viable, both parties may terminate the contract without penalties.
Until when can I request it?
Amendment contracts must be signed by December 31, 2027.
At Reinicke Ostria we advise contractors and supervisors on amendment contracts, price adjustments and termination of contracts with the State. For a consultation, contact us through our contact page.
This document is for information purposes only and does not constitute legal advice. Each case must be assessed individually.